ACM Fire-Retardant vs. Polyethylene Core: What to Put on the Ticket

location

On an ACM/MCM sheet the core is already in the panel when it reaches our floor. The two cores we see are fire-retardant (FR) and polyethylene (PE). FR is the usual specification; PE is available when the specification allows it. CNC Metalcraft® fabricates the sheet that is specified and approved. We will not guess a silent ticket.

Updated November 2026 · CNC Metalcraft

When an ACM sheet arrives on our floor, the core is already in it. CNC Metalcraft® does not build the core. We CNC-route the sheet, form the returns, mark the part and crate it. The two cores we see on tickets are fire-retardant (FR) and polyethylene (PE). FR is the usual specification. PE is available when the specification allows it. If the ticket is silent, we will not guess, and we will not treat “usual” as a substitute for a written requirement.

This article is for the architect or contractor who has to put a core designation on a specification or a purchase order. Product-system language belongs on Sure-Panel® composite panels. The shop facts below are the ones already published on our composite panel systems page and on our home and about pages.

What is the difference, in shop terms?

Both cores sit between two thin aluminum skins in a mill-produced ACM/MCM sheet we run in 3, 4 and 6 mm. The router and the brake follow the same basic path either way. What changes is the requirement on the ticket, and whether the design team has accepted that core for the wall. That acceptance is not a shop preference.

Both cores sit between two thin aluminum skins in a mill-produced ACM sheet. We run those sheets in 3, 4 and 6 mm from Alucobond, Alfrex, Reynobond, Etalbond and ALPOLIC. The router and the brake do not change their basic path because the core is FR or PE. What changes is the requirement on the ticket, and, in many jurisdictions, whether the core is acceptable for the wall in question. That acceptance is a code and specification question, not a fabrication preference.

We do not publish a test claim in this article that is not already on a live CNC page. The live CNC pages state that the Sure-Panel® ACM rainscreen system has been tested to AAMA 508 and ASTM E283, E330 and E331, and that those tests apply to the ACM system only. They do not turn a PE sheet into an FR sheet, or the other way around.

Why do we say FR is the usual specification?

That is the wording on our live product and company pages, and it matches most commercial tickets we see. “Usual” is not “always,” and it is not a code opinion. A project may specify PE. If it does, the specification should say so, and the design team owns whether that choice meets the applicable code.

Because that is the wording on our live product and company pages, and it matches what we see on most commercial tickets. “Usual” is not “always,” and it is not a code opinion. A project can specify PE. If it does, the specification should say so plainly, and the design team is responsible for whether that choice meets the applicable code and the owner’s requirements. We will fabricate the sheet that is specified and approved.

If a set of drawings says “ACM” and nothing else, the quote will have to ask the question. It is cheaper to answer it on the bid form than in a revision after shop drawings are in review.

What should be written on the drawings and the purchase order?

Name the material as ACM/MCM, the thickness (3, 4 or 6 mm), the core (FR or PE), the mill if required, the finish and the system. If we draft, production is about six to eight weeks from shop-drawing approval. If you issue approved fabrication drawings, fabrication takes three to four weeks. Freight is added after that.

Name the material as ACM or MCM, the thickness (3, 4 or 6 mm), the core (FR or PE), the mill if the specification requires a mill, and the finish. Name the system (for example, a dry-joint rainscreen or a wet seal) so the extrusion package matches. Name the delivery city so freight can be estimated. If we draft shop drawings, production takes about six to eight weeks starting when those shop drawings are approved. If you issue approved fabrication drawings, fabrication takes three to four weeks. Freight from Burnsville is added after that and is a planning number, not a carrier bid.

Finish is a separate line. Coil-coated finishes follow the sheet manufacturer. Post-painted finishes are applied by Linetec, as stated on our About page. Do not assume a finish warranty from a core designation; the two are not the same fact.

Put this on the ticket Why the shop needs it
FR or PE, written out “ACM” alone is not a core. We will not infer one.
3, 4 or 6 mm Those are the thicknesses we run.
Mill, if the spec requires one We run Alucobond, Alfrex, Reynobond, Etalbond and ALPOLIC.
System and joint type They drive the extrusion package and the returns.
Delivery address Freight is estimated to the site, not folded into fabrication time.

Does the core change crating or lead time?

Not as a published shop rule. FR and PE ACM/MCM sheets are both routed, formed, marked and crated to protect the finished face. The two clocks — three to four weeks with approved fabrication drawings, or about six to eight weeks of production from shop-drawing approval when we draft — do not split by core.

Not as a published shop rule. FR and PE sheets both get routed, formed, marked and crated to protect the finished face and the returns. The lead-time rules do not split by core. A long haul — about three days to Atlanta or Houston, about four days to Phoenix, as planning estimates — is a freight fact, not a core fact. Receiving in humid or hot markets still means keeping crates off the ground, out of standing water or off hot pavement, and leaving film in place until the panels are ready to hang, following the sheet producer’s guidance.

Who decides whether FR is required?

The design team and the code official. Energy-code editions and climate zones that we cite on state and metro pages do not choose a core for you. Neither does this article. If a specification is still blank on FR or PE, ask the question in writing before shop drawings, or before a fab-only ticket is released.

The design team and the code official. DOE energy-code listings and IECC climate zones, which we cite on our state and metro fabrication pages, are not a substitute for a core decision. Neither is this article. If a specification is still being written, the architect should state the core in the same place they state the thickness and the system. If you are bidding a set that is already written, bid what it says, and ask a written question if it says nothing.

How does this interact with energy-code language on our state and metro pages?

Those pages cite the DOE Building Energy Codes Program for the commercial edition listed in a state, and PNNL-33270 for 2021 IECC climate zones. Those citations help you confirm the edition and the zone. They are not a core specification, and they do not let the shop certify that an ACM/MCM wall meets the energy code.

Our state and metro pages cite the DOE Building Energy Codes Program for the commercial edition listed in each state, and PNNL-33270 for 2021 IECC climate zones. Those citations are about which edition a permit office may be on, and about climate zone, not about which ACM core to buy. A zone 2 job in Phoenix or Houston and a zone 5 job in Chicago or Detroit can both be FR or, if the specification allows it, PE. The zone does not pick the core. The specification and the official do.

The same caution applies to wind notes. Texas TDI catastrophe areas, including parts of Harris County, and Florida’s High-Velocity Hurricane Zone (which is not one of the twelve metros on this workstream) are attachment and design issues for the engineer. They are not a hidden core designation. If a specification in those markets requires a particular core, it should say so in writing.

If you are still choosing a core, write FR or PE in the same sentence as the thickness and the mill, send the set through the quote form, and plan the calendar with the correct fabrication clock. Do not leave the core as a conversation “we can settle later.” Later is how a shop drawing cycle starts twice.

What questions come up most often?

The usual questions are whether FR is the only core we will run (no), whether the shop will say which core passes a local code (no), and whether AAMA or ASTM rainscreen tests pick the core (they do not). The short answers below stay inside the facts already on our live pages.

Is fire-retardant core the only core CNC Metalcraft® will run?

No. FR is the usual specification. A polyethylene core is available when the specification allows it. We fabricate what the approved drawings and the ticket call for.

Can the shop advise which core will pass a local code?

No. Code acceptance stays with the design team and the official who will review the permit. We fabricate to the approved drawings.

Do AAMA or ASTM tests on the ACM rainscreen system choose the core for me?

No. The live CNC pages say those tests apply to the ACM system only. They are not a core specification.

How do I request a quote?

Send a drawing set through the quote form, or call the shop weekdays, 7 a.m. to 4 p.m. Central Time. Put ACM/MCM, the thickness and the core on the ticket so we do not have to guess. The Burnsville address and both shop numbers are in the paragraph below.

Send a drawing set through request a quote, or call (952) 938-3356 or 888.938.3356, weekdays 7 a.m. to 4 p.m. Central Time. CNC Metalcraft®, 11901 Riverwood Dr, Burnsville, MN 55337. Founded in 2005. The plant is over 75,000 sq ft across two Burnsville, MN buildings.