title: How Long Does Metal Panel Fabrication Take?
description: Fabrication is 3–4 weeks with approved fabrication drawings. When we draft, production is about 6–8 weeks from shop-drawing approval. Freight is extra.
---

Call us Today! [**888.938.3356**](tel:8889383356)

[![CNC Metalcraft® Architectural Metal Fabrication logo](https://cncmetalcraft.com/hs-fs/hubfs/cnc-metalcraft-logo-1000.png?width=300&height=73&name=cnc-metalcraft-logo-1000.png) ![CNC Metalcraft® Architectural Metal Fabrication logo](https://cncmetalcraft.com/hs-fs/hubfs/cnc-metalcraft-logo-1000.png?width=300&height=73&name=cnc-metalcraft-logo-1000.png)](https://cncmetalcraft.com)

[![CNC Metalcraft® Architectural Metal Fabrication logo](https://cncmetalcraft.com/hs-fs/hubfs/cnc-metalcraft-logo-1000.png?width=300&height=73&name=cnc-metalcraft-logo-1000.png)](https://cncmetalcraft.com)

<https://cncmetalcraft.com/our-work/fabrication-lead-times-and-shop-drawings#navbar_global>

- Systems 
    - [All Products](https://cncmetalcraft.com/our-products)
    - [Composite Panel Systems](https://cncmetalcraft.com/composite-panel-systems)
    - [Plate Panel Systems](https://cncmetalcraft.com/plate-panel-systems)
    - [Column Cover Systems](https://cncmetalcraft.com/column-cover-systems)
    - [Sure-Panel® S-Lock Tile Panel System](https://cncmetalcraft.com/sure-panel-s-lock-tile-panel-system)
    - [Phenolic](https://cncmetalcraft.com/phenolic)
- [Custom Fabrication](https://cncmetalcraft.com/custom-fabrication)
- Our Work 
    - [View All Our Work](https://cncmetalcraft.com/our-work)
    - [Composite Panel Gallery](https://cncmetalcraft.com/our-work/tag/composite-panel-gallery)
    - [Plate Panel Gallery](https://cncmetalcraft.com/our-work/tag/plate-panel-gallery)
    - [Column Covers Gallery](https://cncmetalcraft.com/our-work/tag/column-covers-gallery)
    - [Tile Panel Gallery](https://cncmetalcraft.com/our-work/tag/tile-panel-gallery)
    - [Phenolic Gallery](https://cncmetalcraft.com/our-work/tag/phenolic-gallery)
- [About Us](https://cncmetalcraft.com/about-us)
- [Contact](https://cncmetalcraft.com/contact-us)

- Systems 
    - [All Products](https://cncmetalcraft.com/our-products)
    - [Composite Panel Systems](https://cncmetalcraft.com/composite-panel-systems)
    - [Plate Panel Systems](https://cncmetalcraft.com/plate-panel-systems)
    - [Column Cover Systems](https://cncmetalcraft.com/column-cover-systems)
    - [Sure-Panel® S-Lock Tile Panel System](https://cncmetalcraft.com/sure-panel-s-lock-tile-panel-system)
    - [Phenolic](https://cncmetalcraft.com/phenolic)
- [Custom Fabrication](https://cncmetalcraft.com/custom-fabrication)
- Our Work 
    - [View All Our Work](https://cncmetalcraft.com/our-work)
    - [Composite Panel Gallery](https://cncmetalcraft.com/our-work/tag/composite-panel-gallery)
    - [Plate Panel Gallery](https://cncmetalcraft.com/our-work/tag/plate-panel-gallery)
    - [Column Covers Gallery](https://cncmetalcraft.com/our-work/tag/column-covers-gallery)
    - [Tile Panel Gallery](https://cncmetalcraft.com/our-work/tag/tile-panel-gallery)
    - [Phenolic Gallery](https://cncmetalcraft.com/our-work/tag/phenolic-gallery)
- [About Us](https://cncmetalcraft.com/about-us)
- [Contact](https://cncmetalcraft.com/contact-us)

# How Long Does Metal Panel Fabrication Take?

location

Fabrication takes three to four weeks when you supply approved fabrication drawings. When CNC Metalcraft® also drafts, production takes about six to eight weeks starting at shop-drawing approval. Freight from Burnsville is estimated separately and is not part of either clock. The two windows are not interchangeable.

Updated November 2026 · CNC Metalcraft

There are two fabrication clocks at CNC Metalcraft®, and they do not start from the same event. If you send approved fabrication drawings, fabrication takes three to four weeks. If we draft the shop drawings, production takes about six to eight weeks, and that clock starts when those shop drawings are approved. A sentence that says “three to four weeks after shop drawings are approved” is not correct, and it will put a jobsite behind.

This article is for general contractors, architects and installers who have to put a hang date on a calendar. It covers what each drawing set is, when each clock starts, how freight from Burnsville, Minnesota sits on top of those clocks, and what to send so we can quote the right one. System options and specifications live on [the Sure-Panel® FAQ](https://www.sure-panel.com/faq) and the Sure-Panel® system pages; this page stays with the shop.

## What is the difference between fabrication drawings and shop drawings?

Fabrication drawings are the approved set you send us to cut and form from. Shop drawings are the set we issue for your review when drafting is in our scope. On a drafting job, production starts only after those shop drawings are approved. Mixing up the two sets is how the clocks get collapsed.

Fabrication drawings are the set your design team (or another detailer) issues for manufacturing. When that set is already approved, our shop can go to work on it. Shop drawings are the set we prepare in Burnsville when drafting is part of our scope. We issue them for your review. Every part later carries a mark that matches the approved shop drawings.

The two sets can describe the same wall. The difference is who produces them and when the production clock is allowed to start. Mixing the two is the most common scheduling mistake we see on bid forms and in published articles.

## When does the three-to-four-week fabrication window apply?

It applies when approved fabrication drawings are already in your package. We then fabricate, mark and crate the ACM/MCM, plate or column-cover work in three to four weeks. That window does not start at shop-drawing approval, and it does not include freight from Burnsville to the jobsite.

It applies when your team provides approved fabrication drawings. In that case, CNC Metalcraft® fabricates the work in three to four weeks. The clock is a fabrication clock, not a drafting clock. It does not start on the day shop drawings — drawings we would have issued — are approved, because those shop drawings are not part of the job.

If the fabrication drawings still need a revision cycle, say so. We cannot honestly start a three-to-four-week fabrication window on a set that is not approved.

## When does the six-to-eight-week production window apply?

It applies only when we draft. We issue shop drawings, you approve them, and production then runs about six to eight weeks from that approval date. If you already have approved fabrication drawings, this longer clock does not apply. Freight is still added after the crates are ready.

It applies when drafting is in our scope. We prepare shop drawings, you review them, and production takes about six to eight weeks starting on the approval date of those shop drawings. The approval date is the start, not the day the first sketch left our office, and not the day the bid was awarded.

Build the hang date backward from that approval, then add fabrication or production, then add freight, then add unloading and a modest buffer. Do not build it forward from a hoped-for start date on the proposal.

## How should freight be added to the calendar?

Add freight after the fabrication or production window, not inside it. We estimate transit from Burnsville using a planning method, and we label the figure as an estimate, not a carrier bid. A one-day Midwest run and a three- or four-day long haul are scheduled the same way: crates first, then the truck.

Freight is a third number, and it is not included in either fabrication window. We ship nationwide from 11901 Riverwood Dr, Burnsville, MN 55337. On our metro fabrication pages we publish planning mileages — a great-circle distance times a 1.2 road factor, with days equal to that mileage divided by 500, rounded up. Those figures are schedule aids, not a carrier’s bid.

Examples from those pages (all estimates): about one day to [Chicago](https://cncmetalcraft.com/metal-panel-fabrication/illinois/chicago) or [Kansas City](https://cncmetalcraft.com/metal-panel-fabrication/missouri/kansas-city); about two days to [Columbus](https://cncmetalcraft.com/metal-panel-fabrication/ohio/columbus), [Indianapolis](https://cncmetalcraft.com/metal-panel-fabrication/indiana/indianapolis), [Detroit](https://cncmetalcraft.com/metal-panel-fabrication/michigan/detroit), [St. Louis](https://cncmetalcraft.com/metal-panel-fabrication/missouri/st-louis), [Denver](https://cncmetalcraft.com/metal-panel-fabrication/colorado/denver) or [Nashville](https://cncmetalcraft.com/metal-panel-fabrication/tennessee/nashville); about three days to [Dallas–Fort Worth](https://cncmetalcraft.com/metal-panel-fabrication/texas/dallas-fort-worth), [Houston](https://cncmetalcraft.com/metal-panel-fabrication/texas/houston) or [Atlanta](https://cncmetalcraft.com/metal-panel-fabrication/georgia/atlanta); about four days to [Phoenix](https://cncmetalcraft.com/metal-panel-fabrication/arizona/phoenix). A tight downtown site may also need a smaller truck or an off-hours window, which belongs on the order before the crate leaves the dock.

## What belongs in the quote request so the right clock is priced?

Send elevations, quantities, the material (ACM/MCM, plate or covers), thickness or core, finish, the joint or system, and the delivery address. Say whether you will issue approved fabrication drawings or want us to draft. That single choice is what selects the three-to-four-week clock or the six-to-eight-week clock.

Send elevations, approximate square footage, the system and material, the finish, and the delivery address. Say plainly whether you will issue approved fabrication drawings or whether you want us to draft shop drawings. If drafting is in our scope, the six-to-eight-week production window is the one to plan around, and it does not start until approval. If you already have approved fabrication drawings, attach them and plan on a three-to-four-week fabrication window after we have a complete, approved set in hand.

You can start that conversation on our [quote form](https://cncmetalcraft.com/request-a-quote) or by calling the shop. [Custom fabrication](https://cncmetalcraft.com/custom-fabrication) describes the equipment side: shearing, bending, punching, rolling and welding, with material up to 16 feet through the brake and rolls. Column covers, which are a frequent source of schedule questions, are made as a single piece up to 15 feet; taller covers ship as marked stacked sections. See [column cover systems](https://cncmetalcraft.com/column-cover-systems) and our article on covers taller than 15 feet.

| Situation | Clock | When it starts |
| --- | --- | --- |
| You issue approved fabrication drawings | Three to four weeks of fabrication | When the approved fabrication drawings are in our hands and the job is released to the floor |
| We draft the shop drawings | About six to eight weeks of production | On the day those shop drawings are approved |
| Freight from Burnsville | Planning days by destination (see metro pages) | After crates are ready; not part of either fabrication window |

State-by-state fabrication notes, including energy-code listings from the DOE Building Energy Codes Program, are on the [fabrication-by-state index](https://cncmetalcraft.com/metal-panel-fabrication).

## What does a worked example look like, so the two clocks stay distinct?

If you send approved fabrication drawings on Monday, fabrication is three to four weeks from that point, then freight. If we draft instead, the six-to-eight-week production clock starts only when you approve the shop drawings, not when the bid set arrives. The two examples should never be averaged together.

Suppose an installer in Columbus needs panels on site at the beginning of a week, and drafting is in our scope. Work backward. Two days of transit (a planning estimate on the [Columbus metro page](https://cncmetalcraft.com/metal-panel-fabrication/ohio/columbus)) means the crates should leave Burnsville earlier in the prior week. About six to eight weeks of production must already have run, and that production did not start on bid day — it started when the shop drawings were approved. If approval slips a week, the hang date slips a week. The freight estimate does not absorb an approval delay.

Now flip the example. The same Columbus installer issues approved fabrication drawings and does not ask us to draft. The fabrication window is three to four weeks, not six to eight, and it is a fabrication window, not a shop-drawing window. Freight is still about two days on top. The hang date is earlier only if the approved fabrication drawings really are approved, complete, and in our hands when the job is released to the floor.

## Why is this wording worth being strict about?

Logged-out answer engines have already collapsed the two clocks into a single sentence that is not how this shop works. A schedule written from that sentence will miss a drafting job or overstate a fab-only job. Keeping the wording exact on this page, and on our metro pages, is how we stop that from spreading.

Short marketing lines often collapse the two clocks into one sentence: “three to four weeks, or six to eight with shop drawings.” That shorthand leaves out the start date, and it is easy to read as “three to four weeks after shop drawings are approved.” We have corrected our own draft state and metro pages so they never use that sentence. Anyone writing a specification, a bid calendar or a blog post should do the same.

Installers who have a question about a mark or a drawing once the crates are on site can call the Burnsville shop on weekdays, 7 a.m. to 4 p.m. Central Time. That field support does not change either clock, but it is part of how a job actually finishes after the truck arrives. Photos of completed buildings, described by building type and city, are on [our work](https://cncmetalcraft.com/our-work).

## What questions come up most often?

The questions we hear most are whether fabrication always starts after shop-drawing approval (it does not), whether freight sits inside either clock (it does not), and what happens if drawings change after approval. Short answers are below; the sections above spell out the same rules in more detail.

### Is fabrication always three to four weeks after shop drawings are approved?

No. That wording is incorrect. The three-to-four-week window is fabrication, and it applies when you supply approved fabrication drawings. The six-to-eight-week window is production, and it starts when our shop drawings are approved, only if we did the drafting.

### Does freight count as part of the three-to-four or six-to-eight-week window?

No. Freight is estimated separately, from Burnsville to the delivery address, and should be added after the fabrication or production window.

### What if we change the drawings after approval?

A change after approval can restart or extend the clock. Tell us as soon as the change is known so the hang date can be revised honestly.

## How do I request a quote?

Send a drawing set through the quote form, or call the shop on a weekday between 7 a.m. and 4 p.m. Central Time. Name the delivery city and whether drafting is in our scope so we can apply the correct ACM/MCM or plate clock. The Burnsville address and both shop numbers are in the paragraph below.

Send a drawing set through [request a quote](https://cncmetalcraft.com/request-a-quote), or call (952) 938-3356 or 888.938.3356, weekdays 7 a.m. to 4 p.m. Central Time. CNC Metalcraft®, 11901 Riverwood Dr, Burnsville, MN 55337. Founded in 2005. The plant is over 75,000 sq ft across two Burnsville, MN buildings.

[![CNCmetalcraft-logo](https://cncmetalcraft.com/hubfs/CNCmetalcraft-logo.png)](https://cncmetalcraft.com)

11901 Riverwood Dr  
Burnsville, MN 55337

- <https://www.facebook.com/CNCMetalcraft/>
- <https://www.instagram.com/cncmetalcraft/>
- <https://www.linkedin.com/company/cnc-metalcraft/>

### Quick Links

- [Leed](https://cncmetalcraft.com/leed)
- [Resources](https://cncmetalcraft.com/resources)
- [Documentation](https://cncmetalcraft.com/documentation)

### Stay in Touch

Copyright © 2026 CNC Metalcraft | All rights reserved | [Privacy Policy](https://cncmetalcraft.com/privacy-policy) | [Terms of Use](https://cncmetalcraft.com/terms-and-conditions-of-use) 

```json
{
					"@context": "http:\/\/schema.org\/",
					"datePublished": "2026-11-24T11:06:07 PM",
					"dateModified": "2026-11-24T11:16:13 PM",
					"headline": "How Long Does Metal Panel Fabrication Take?",
					"description": "Fabrication is 3&ndash;4 weeks with approved fabrication drawings. When we draft, production is about 6&ndash;8 weeks from shop-drawing approval. Freight is extra.",
					"mainEntityOfPage": {
						"@type": "WebPage",
						"@id": "https://cncmetalcraft.com/our-work/fabrication-lead-times-and-shop-drawings"
					},
					"author": {
						"@type": "Person",
						"name": "CNC Metalcraft",
						"url": "https://cncmetalcraft.com/our-work/author/cnc-metalcraft"
					},
					"publisher": {
						"@type": "Organization",
						"name": "Sure-Panel&reg;, Aluma Fab Metal Sales, Protean Construction Products - Subsidiaries of CNC Metalcraft&reg; Company",
						
					},
					
					"image": {
						"@type": "ImageObject",
						"url": "https://cncmetalcraft.com/hubfs/cnc-favicon-48-1.png"
					},
					
					"name": "How Long Does Metal Panel Fabrication Take?"
				}
```

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "CNC Metalcraft",
    "url" : "https://cncmetalcraft.com/our-work/author/cnc-metalcraft"
  },
  "dateModified" : "2026-11-24T23:16:13.087Z",
  "datePublished" : "2026-11-24T23:06:07.000Z",
  "headline" : "How Long Does Metal Panel Fabrication Take?",
  "mainEntityOfPage" : {
    "@id" : "https://cncmetalcraft.com/our-work/fabrication-lead-times-and-shop-drawings",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://cncmetalcraft.com/hubfs/CNCmetalcraft-logo.png"
    },
    "name" : "CNC Metalcraft"
  }
}
```

```json
{
  "@context" : "https://schema.org",
  "@id" : "https://cncmetalcraft.com/our-work/fabrication-lead-times-and-shop-drawings#faq",
  "@type" : "FAQPage",
  "mainEntity" : [ {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "No. That wording is incorrect. The three-to-four-week window is fabrication, and it applies when you supply approved fabrication drawings. The six-to-eight-week window is production, and it starts when our shop drawings are approved, only if we did the drafting."
    },
    "name" : "Is fabrication always three to four weeks after shop drawings are approved?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "No. Freight is estimated separately, from Burnsville to the delivery address, and should be added after the fabrication or production window."
    },
    "name" : "Does freight count as part of the three-to-four or six-to-eight-week window?"
  }, {
    "@type" : "Question",
    "acceptedAnswer" : {
      "@type" : "Answer",
      "text" : "A change after approval can restart or extend the clock. Tell us as soon as the change is known so the hang date can be revised honestly."
    },
    "name" : "What if we change the drawings after approval?"
  } ],
  "url" : "https://cncmetalcraft.com/our-work/fabrication-lead-times-and-shop-drawings"
}
```